The Road Rehabilitation program is a road reconstruction and resurfacing program that is completed annually.

The 2020 program included the following locations:

  1. Welland Road between Arbour Circle and Hunter’s Ct.
  2. Arbour Circle
  3. Townsend Circle
  4. Milburn Drive
  5. Woodside Square (from Welland Road to 70 m North of Meadowbrook Lane)
  6. Kevin Drive (from Haist Street to Sherri Lee Cres.)
  7. Sherri Lee Cres.
  8. Meadowvale Drive

Due to weather constraints the following locations will be completed in the spring of 2021: 

  1. Woodside Square (from Welland Road to 70 m North of Meadowbrook Lane)
  2. Kevin Drive (from Haist Street to Sherri Lee Cres.)
  3. Sherri Lee Cres.
  4. Meadowvale Drive

Driveway restoration and asphalt replacement adjacent to areas that had curb and gutter repairs will be completed prior to the winter shut down.