2017-PW-37 Maple Street Culvert Replacement
Project Duration: September 26 - October 20, 2017, weather dependent
Project Location: Maple Street, Between Sixteen Road and Kilman Road
Project Description: Contractors will be working on Maple Street to complete the replacement of twin culverts located on Maple Street, south of Sixteen Road. Due to the nature of the work, Maple Street will be closed to all through traffic during the project duration. Local access will be permitted from Kilman Road. Residents are instructed to follow detour signs to Balfour Street.
Project Contact: Matt Sferrazza, engineering technologist 905-892-2607 x342
Tolga Aydin, engineering technologist 905-892-2607 x330